Archive for June, 2008

Published by admin on 28 Jun 2008

Pebble Creek is approved

At the public meeting held on June 25, 2008, the ballots for the proposed Pebble Creek annexation were counted. The proposal was overwhelmingly approved. Here are the numbers:

  1. 499 Ballots Returned
  2. 446 Valid Ballots
  3. 420 Voted Yes
  4. 26 Voted No
  5. 53 Ballots were invalid
  6. 94% Approval of the proposal

The next step is for Pebble Creek to request annexation into Plat 2 from Wasatch County. The request must be approved by both the County Planning Commission and the County Council. This process will take a few months. If the annexation is approved by the County, then Pebble Creek will become part of Timber Lakes.

We appreciate everyone who participated, asked questions, attended the meetings and took part in this matter. We will keep you informed as the process continues.

Published by admin on 27 Jun 2008

We have started construction

Good news. On June 12th the County Council met and, after taking public comment and having members of the Timber Lakes Board answer some key questions, approved our Revised Conditional Use Permit. With that approval we were able to move forward and start construction.

Our contractor, Double P Construction, started working late last week and has now completed footing excavation, tied a portion of the rebar and is pouring footings for half of the building on Friday the 27th. The remainder of the footings will go in early next week, with foundation walls following immediately thereafter.

I will try to have a couple of new photos every week, along with a brief description of what is happening. You will be able to see the progress in person or by checking our website and clicking on the page labeled Maintenance Building Progress.

Ole Smith

Published by admin on 17 Jun 2008

County Council approves the water project

The Wasatch County Council held a follow-up information meeting tonight at 7:00 p.m. in the Wasatch County Senior Citizens Center. The purpose of the meeting, as outlined in the letter posted in my previous blog, was to inform the Timber Lakes property owners of the construction bids and other cost changes in the proposed water distribution system improvements and to give owners a chance to ask questions.

Council Chairman Steve Farrell reviewed the revised cost estimates for the project, which are outlined in the above referenced letter. The cost was reduced almost $4 million by obtaining hard cost bids on materials and construction. Another $1 million was reduced by opting for a basic telemetry system than can be added to over time rather than purchasing a complete system up front and by having the Water Company crew perform spring development rather than contracting that piece out. Adding a contingency fund for unforeseen problems of $.5 million increased the cost. The construction period interest decreased by approximately $20,000, with the construction likely taking three years to complete rather than two, although that is still an open issue. The net total changes are a reduction of approximately $4.9 million. This is projected to cost each lot $6,400 up front or $44 per month for twenty years.

The Chairman opened the meeting for public questions. The following is my personal recollection of items that were clarified by the Council or the Water Board during the Public Question period. If the Council approves the project tonight, construction will begin within 30 days. It will take 2-3 years to complete the project. Some of the costs are still just estimates but the estimates should not be exceeded. Hard costs on some items cannot be calculated yet as some items still need to be designed. There are still opportunities to further reduce costs and the Council and Water Board are interested in finding all the savings possible. The final amount of the upfront assessment fee and the monthly assessment fee will not be known until construction is complete. Property owners will not have to start paying for the project until construction is complete. This gives owners 2-3 years to come up with the upfront payment or decide to pay it monthly. In addition, at anytime during the twenty-year period, an owner can get a payout amount from the Water Company and pay off the balance without penalty. The interest rate used to calculate the monthly $44 payment amount is 5.5%. The actual numbers will not be known until construction is complete and the bond has been sold. However, the total cost of the project, if approved, cannot exceed the $9,387,000 estimated. The Water Board has been asked by the Council to come up with a procedure for allowing people to combine contiguous lots for the purpose of eliminating a double water assessment if the owner wishes to bind the property forever that no water hookup can be provided to the additional lot. Concern was expressed for the financial burden this project places on individuals. The Council has pared the costs down and cannot see an alternative that is better than making the proposed improvements. With the exception of one owner stating he considered the whole project to be illegal and that it should be stopped until someone figures out a better way, no one proposed other alternatives. The cost estimates have taken into consideration the impact of combining lots and the potential impact of non-paying lot owners. Jody Defa, of the Water Company was asked to comment on ways that the Water Company’s crew could reduce costs by doing things themselves. Mr. Defa stated that he was always wiling to help property owners in any way possible. He pointed out his crew is limited in how much they can handle. We run the risk of not having water during the winter months and at other times when things are broken or leaking. He expressed the opinion that it would be very difficult if we did not do something to address the problems. Finally, it was noted that the Water Board does have the authority to raise rates if they decided it would be better to have a rate increase during the construction period. This amount would then presumably offset the amount that would have to be bonded at the completion of construction. Council was asked why it was in such a hurry to decide this issue. Chariman Farrell replied that the bid for materials and construction was valid for only 30 days.

The Chairman closed the public question portion of the meeting and the County Council held a discussion about the project, clarifying legal, financial and operational issues. They expressed concern about the financial burden on people but felt it will cost even more if we continue along as we have been doing. No one wants to be addressing this again in five years.

In the end, the Council voted 7-0 to approve the special assessment area to bond the project for an amount not to exceed $9,387,000. They instructed the Water Board to come back within 30 days with a recommended procedure for combining lots.

Bottom line: the water distribution system will be replaced. Construction begins next month. Gary Hume, a member of the TLPOA Board of Directors will attend all Water Board meetings and will be our liaison between the property owners and the Water Company. Your TLPOA Board will continue to look for ways to help cut the cost and work with the Water Board to limit the confusion and disruption to life on the mountain.

Published by admin on 13 Jun 2008

Update on the Proposed Water Improvement Assessment

We have received the following IMPORTANT update from the Timber Lakes Water Company. Please read the following letter. There is a public meeting on Tuesday, June 17, 2008 at 7:00 pm at the Wasatch County Senior Citizens Center to update the public on the latest information regarding this matter.

If you cannot read the text size of the letter, please click here to open the letter as a pdf file, which you can print or zoom in.

Published by admin on 12 Jun 2008

Maintenance Building is Approved and Bid

After several months of planning and designing the modifications required by Wasatch County, we finally have a set of approved plans, and bids are in, from several General Contractors and Sub-Contractors. Construction is now ready to commence on our new vehicle storage and maintenance building.

On June 5th Ole Smith, the Board member assigned to supervise our construction, paid the building permit fees and picked up the signed, approved building permit from the County. The plans had already been out to bid for about 3 weeks so the next day, June 6th, bids were received from all the contractors. Over that weekend of June 6-9 the bids were painstakingly analyzed and the winning bidder, Double P Construction, was selected. Double P will also be working with us to find additional ways to reduce our costs, including allowing us to self-perform some work, possibly use some local Timber Lakes subcontractors who have offered us great pricing for their trade, and work with us on some value-engineering efforts.

Double P plans to start construction the week of June 16-20 and be finished approximately120 days later, in mid-October.

There is, however, one last hurdle we still need to clear. When we first started the proposal of building last year, the County, while still checking our building plans for code compliance, moved forward and approved our Conditional Use Permit. In very simplified terms, a Conditional Use Permit is the approval to place something other than a residential building on a lot and, when approved, the building must be placed exactly where it is shown on the submittal, plus the owner must agree to follow any other “conditions” that are given by the County Commission. On the other hand a Building Permit is approved when the plans submitted by an owner meet all the building codes and requirement for safe and proper construction. In our case the approved Conditional Use Permit showed all the big bay doors facing north (right where all the snow falls and ice freezes and never melts off… because it receives no winter sun.) When the mistake was discovered we needed to go back and ask the County for a Revised Conditional Use Permit to allow us to rotate the building orientation to a west-south-west direction…thus receiving some winter sun. This request is scheduled for a County hearing on June 12th. We tentatively expect approval of this request but it is not a sure thing until approved. Check the website regularly and we’ll tell you how it went.

You can check out our building progress by watching for regular construction photos which will be posted on the website as soon as we begin. Click on Maintenance Building Progress and watch it rise.

If you have any questions feel free to email me, Ole Smith, at MaintBuilding@TimberLakesUtah.com.